Construction MKM Builders Merchants
Duration // 29 Week

Construction of new warehouse and storage yard.

Location // Boston

NU Construction completed a competitive tender for a new industrial development at Boston, Lincolnshire for MKM. NU Construction were selected to develop the design and build scheme with the client and the contract administrator.

The works comprised the design and build, inclusive of a steel frame, clad building with storage mezzanine for use as a nationwide builder’s merchant.  External works consisted of concrete yards, car parking, S278 highways works with associated external storage, access, column lighting and fencing.

Site investigations were carried out by the client prior to appointing N U Construction.  The contract to start works stated that no obstructions or contamination were present within the ground of the site. NU Construction carried out a proof dig and recorded all findings to the footprint of the building in advance of the piling commencing, thus identifying any issues prior and mitigating costs and delays.

This identified areas of concern and a delay caused because of the removal of an unchartered borrow pit underneath the building which had asbestos containing material (ACM’s). NU Construction sought the approved contractor to carry out air monitoring, testing, safe removal, and clearance. This allowed NU Construction to progress and accommodate the clients’ fit-out team to complete their work on time.

Latest Projects.

  • Liverpool//
  • National Farmers Union Mutual

2-8 Church Street

read more
  • Rotherham//
  • Parseq

Warehouse Extension

read more
  • Redditch//
  • Kettler (GB)

Warehouse Extension

read more
  • Heckmondwike//
  • LCP Properties

Unit 1 Retail Unit, Heckmondwike

read more
  • Holme Valley//
  • Kirklees PCT

Holme Valley Hospital

read more
  • Rochdale//
  • Eric Wright Partnership Ltd

Kirkholt Medical Centre

read more

It is an enormous credit to your team the building was ready and that the work had been completed to such a high standard.

  • Sir John Townsley BA (Hons) NPQH.
  • Executive Principal.
  • The Gorse Academies Trust

It is an enormous credit to your team the building was ready and that the work had been completed to such a high standard.

  • Sir John Townsley BA (Hons) NPQH.
  • Executive Principal.
  • The Gorse Academies Trust